Goulamina Lithium Project: Q1 2026 Production Update
Record material movement as ramp-up continues
- Home
- News & Updates
- Goulamina Lithium Project: Q1 2026 Production Update
The Goulamina Lithium Project in southern Mali has continued its strong operational performance through the first quarter of 2026, with Corica's mining team delivering record material movement volumes as the project progresses through its ramp-up phase.
Q1 2026 Key Metrics
2.1M
BCM Moved
340K
Tonnes Ore
98.2%
Fleet Availability
Pit Development Progress
Mining operations in the main Goulamina pit have advanced to the Stage 2 cutback, with benching now at the 345-metre reduced level. The ore body exposure is tracking ahead of schedule, providing the processing plant with a consistent feed grade of spodumene-bearing pegmatite.
Waste haulage to the eastern dump has been optimised through a revised road network design, reducing average cycle times by approximately 12% compared to Q4 2025. This improvement has been a direct result of the planning team's work on traffic flow modelling and the commissioning of a new water cart rotation to maintain road surface quality.
Rainy Season Preparedness
With the West African rainy season approaching in June, the team has commenced early preparation of dewatering infrastructure around the pit perimeter. Sump capacity has been increased by 40% compared to the 2025 wet season, and additional pumping equipment has been mobilised from the Bamako workshop.
"Rainy season at Goulamina is always a challenge given the scale of the pit," said the Goulamina Site Manager. "Last year we lost approximately 15 days of productive mining to weather events. This year, with improved drainage infrastructure and a dedicated dewatering crew, we're targeting less than 8 days of lost time."
Fleet Performance
The CAT 6030 and CAT 777 fleet has maintained an average mechanical availability of 98.2% for the quarter — a figure that reflects the maintenance team's disciplined approach to preventive scheduling. Zero major component failures were recorded during Q1, compared to two in Q1 2025.
Q2 2026 Outlook
The second quarter will focus on commencing the Stage 3 cutback design and expanding the waste dump footprint to accommodate increased stripping ratios. An additional CAT 777 is expected to be commissioned in April, bringing the total haul fleet to 14 units.
About the Goulamina Lithium Project
Owned by Ganfeng Lithium subsidiary Leo Lithium, the Goulamina project is one of the world's largest and highest-grade hard-rock lithium deposits.
Article Information
Mark Gabbedy
March 31, 2026
6 min read
Bougouni, Mali
More News & Updates
Corica Mining Services Launches New Digital Platform
A complete reimagining of how Africa's leading mining services provider connects with clients, partners, and future team members
Corica at LIMEC 2026 in Liberia
An excellent AME Trade event showcased Liberia's opportunities for mine owners and their partners.
CORICA Mining Services Featured in Mining Outlook Issue 14
Comprehensive feature on CORICA's integrated approach to contract mining